2016 Road Resurfacing Project

Print
Press Enter to show all options, press Tab go to next option

The Town of Portola Valley will be performing street resurfacing on portions of the below listed streets. This project will consist of applying surface seals to the road surface. Work is scheduled to take place between the dates listed below, weather permitting.  The repairs will include grinding worn areas, crack sealing, a surface seal treatment, and repainting traffic markings.

Traffic will have limited access through these streets during the street resurfacing process. Traffic controls within the construction area will be in place. Normal construction hours are Monday through Friday from 8:00 a.m. to 5:30 p.m.  Two days prior to construction, “No Parking” and “Tow-away” signs will be posted with the effective time and date.  Roads will be reopened to full traffic and parking at the end of each working day, however, during the construction period, loose gravel and an uneven pavement surface will result from removing the surface asphalt.  For the entire project, we estimate it will take 2 weeks to repair damaged pavement sections, 1 week to remove traffic striping, 1 week to apply surface seals, and 1 week to repaint traffic markings. To maintain competitive prices, the contractor, G. Bortolotto & Co., Inc. is allowed to schedule the work in a cost effective manner which may result in a time lag between repair, required curing times, and resurfacing.


PROJECT SCHEDULE

 

Phase 1 Phase 2 Phase 3
Street Name From To Treatment Crack Seal Dates Base Repairs Dates Surface Seal Date with No Road Access
1 Alhambra Court Entire length Entire Length Microsurfacing Mon-Thur, 5/16-5/19 Wed-Fri, 5/18-5/20 AND Mon & Tues, 5/23 & 5/24 Wednesday, June 15th
2 Alpine Road Willowbrook Drive Corte Madera Road Slurry Seal Mon-Thur, 5/16-5/19 Mon-Wed, 5/16-5/18 Monday, June 13th
3 Ann Road Entire length Entire length Slurry Seal Mon-Thur, 5/16-5/19 Mon-Fri, 5/24-5/27 Tuesday, June 14th
4 Cervantes Road Arapahoe Court Shawnee Pass (East end) Slurry Seal Mon-Thur, 5/16-5/19 Wed-Fri, 5/18-5/20 AND Mon & Tues, 5/23 & 5/24 Tuesday, June 14th
5 Cherokee Court Entire Length Entire Length Slurry Seal Mon-Thur, 5/16-5/19 Wed-Fri, 5/18-5/20 AND Mon & Tues, 5/23 & 5/24

Monday, June 13th

Wednesday, June 15th

6 Cherokee Way Entire length Entire length Slurry Seal Mon-Thur, 5/16-5/19 Wed-Fri, 5/18-5/20 AND Mon & Tues, 5/23 & 5/24 Wednesday, June 15th
7 Corte Madera Road Portola Road Alpine Road Surface Reconstruct/ Slurry Seal Mon-Thur, 5/16-5/19 Mon-Wed, 5/16-5/18

Reconstruction: Fri & Wed, 5/27 & 6/1.

 

Surface Seal: Tuesday, June 14th; Alpine Rd. to Cima Way and Wednesday, June 15th; Cima Way to Portola Rd.

8 Degas Road Entire Length Entire Length Microsurfacing Mon-Thur, 5/16-5/19 Tuesday, June 14th
9 Escobar Road Entire length Entire length Microsurfacing Mon-Thur, 5/16-5/19 Mon-Fri, 5/24-5/27 Monday, June 13th
10 Granada Court Entire Length Entire Length Slurry Seal Mon-Thur, 5/16-5/19 Wed-Fri, 5/18-5/20 AND Mon & Tues, 5/23 & 5/24 Wednesday, June 15th
11 Indian Crossing Alpine Road Valley Oak Slurry Seal Mon-Thur, 5/16-5/19

Only Northbound Tuesday, June 14th

Only Southbound Wednesday, June 15th

12 Larguita Lane Entire length Entire length Slurry Seal Mon-Thur, 5/16-5/19 Monday, June 13th
13 Los Trancos Road Near Oak Forest Court Town Limits Microsurfacing Mon-Thur, 5/16-5/19 Mon-Fri, 5/24-5/27

Only Northbound Tuesday, June 14th

Only Southbound Wednesday, June 15th

14 Solana Road Entire Length Entire length Slurry Seal Mon-Thur, 5/16-5/19 Mon-Fri, 5/24-5/27 Monday, June 13th 
15 Westridge Drive 1145 Westridge Drive Paloma Road Slurry Seal Mon-Thur, 5/16-5/19 Mon-Wed, 5/16-5/18

Only Southbound Monday, Monday, June 13th

Only Northbound Tuesday, June 14th

16 Westridge Drive Cervantes Road (West end) Portola Road Slurry Seal Mon-Thur, 5/16-5/19 Mon-Wed, 5/16-5/18

Only Southbound Monday, Monday, June 13th

Only Northbound Tuesday, June 14th

 

 

* The final coat requires 4-5 hours of cure time weather permitting before touching. Please plan travel and schedule arrangements accordingly.  

* Door hangers will be passed out as a reminder 48 hours in advance 

* Pot hole/base repairs will be performed in advance of the surface seal. Expect minor traffic delays.

* In the surface seal process, there can be material cure times of up to 1 week between the asphalt repair process and the application of the surface seal top coat.

Note: The contractor will be hand delivering printed notices to residents 2 days in advance indicating the exact date your street is scheduled for the surface seal treatment phase which may affect access until the surface has cured and dried enough to allow traffic.  Please do not water or drive on surfaces until dried, it will affect the final look of the product and track onto surfaces. The garbage company and postal service will also be notified to make arrangements. 

We are aware that there will be residents who will be inconvenienced by the street resurfacing work and we ask for your cooperation and understanding. These improvements will result in an improved street that will serve the area for many years. 

G. Bortolotto & Co., Inc. (650-595-2591)
On-Site Public Works Inspector: Frank Vargas (925-285-9011)
Public Works Director: 
   Howard Young, (650-851-1700 x214)